San Francisco 1:         electrics         painting         bathroom         kitchen

november 2003 duration: 3 months

complete reforming job, rewiring, water connection, gas connection, painting, bathroom (tiling in second phase), kitchen.
design, planning and paint work by works XL, wiring and water connetion by Roca, gas connection by Invesgas (hot water only, no heating)
total cost (not including design work) 12.352,07 euros
electrics: 8.000 euros, gas: 2.412,07 euros, painting (just walls): 1.000 euros, bathroom tiling: 340 euros, kitchen (just new cabinet doors): 600 euros

complete new installation on 7 circuits with new counter and new fusebox all under surface except the main lines in the hallway.

  before planning materials cost inbetween done  