Sant Crispí:         electrics         floor         painting         kitchen

april 2005 duration: 7 days

design and work exclusively by works XL. reforming in 4 stages: first the floor, then electrics, then painting, then the new kitchen.
the apartment is used for summer rentals so a brighter design then one would use at home.

rewiring maintaining the basic structure to the main fuse downstairs, replacing all switches and plugs from brown old to white modern ones.

total cost (not including design work) 10.841,10 euros

  before planning materials cost inbetween done  