january 2005 duration: 15 days
design and work exclusively by works XL. reforming in 4 stages: first the floor, then electrics, then painting, then the new kitchen. diagonal tiling makes the fairly small rooms look wider. tiled on top of the old granite floor which was still in good conditon, just very ugly. total cost (not including design work) 10.841,10 euros |
|||||||
| before | planning | materials | cost | inbetween | done | ||
![]()
|
|
![]() ![]() ![]() ![]() ![]()
|
|||||